July Capital Project Update: Major progress!

July Capital Project Update: Major progress made!
Posted on 07/10/2020
 Pictures of the projects
 

Dry summer weather and efficient work by Campus Construction have helped move along several different jobs at a few different schools in our Renewal Project. Here are some highlights:

Irondequoit High School

  • Roof replacement is nearly complete; metal flashing work will be on-going in July and August.
  • The gymnasium floor has been removed and new hoops installed; installation of the new floor will begin soon.
  • Demolition on the front (main) entrance foyer/vestibule began in late June, right after graduation ceremonies wrapped up. New security walls will be built in July; doors also will be replaced.
  • Locker room renovations are down to the final stages; tile work should end before school starts.

 Dake Junior High School

  • Concrete work outside was completed in June.
  • Major renovations of the main office are moving along well; painting and floor prep is scheduled for July.
  • Renovations/framing of the new main entrance vestibule also are under way.

 Iroquois Middle School

  • Roof work is complete.
  • Classroom carpet replacement is on-going.
  • New concrete will be poured for a walkway on the building’s east side.

 Rogers Middle School

  • Work on walls in the basement corridor has begun
  • New carpet installation begins later in July

 Colebrook & Southlawn

  • New playgrounds were completed and re-opened in June.
For all Capital Project updates, visit our page at this link.